Carbon Steel Piping & Structures
     

Location: 

    Tower Semiconductor LTD
Customer:   Tower Semiconductor LTD
Period:   1997
Description:   PILOT FAB2 Profile platform installation inside Clean Room environment for IMPLANTER – about 20 ton steel
     
Location:    Tower Semiconductor LTD
Customer:   Tower Semiconductor LTD
Period:   1997
Description:   TOWER FAB1 INTERSTITIAL floor – about 250 m² of steel beams and catwalk above IMPLANTER CENTER
     
Location:    Intel, Kiryat Gat, FAB18
Customer:   Intel
Period:   2007
Description:   Fire Protection for INTEL FAB18 New Sort
     
Location:    Intel, Kiryat Gat, FAB18
Customer:   LBA
Period:   2006-2007
Description:   Installation of 200,000 m of unistrat, supports for Intel, FAB28 systems
 

 

 Location:     Ceaserstone Sdot-Yam
 Customer:    Ceaserstone
 Period:    2014
 Description:    Vacuum system – production lines on the roof: galvanized pipes, fittings and dampers up to Ø1200 mm
     
  Location:     Ceaserstone Bar-Lev and Sdot-Yam
 Customer:    Ceaserstone
 Period:    2014-15
 Description:    Manufacture and supply of 3 Modular structures